Oregon General Journeyman Study Pack
Everything for the Oregon General Journeyman (J) exam on the 2026 NEC
Written for the 2026 NEC. Last updated October 2026. Corrections
$149Launch price
One-time payment. Yours to keep, no subscription.
30-day refund. If the pack doesn't help you, send me a note within 30 days of buying and I'll refund you. No hoops.
Secure checkout by Stripe. Card details never touch this site.
Not sure yet? Read the Box Fill chapter free, no account needed.
Written by a journeyman licensed since 1999 for the open-book Oregon General Journeyman (J) exam: 52 questions, 3 hours, 75% to pass, 2026 NEC plus Oregon's amendments and rules.
- Study chapters on finding answers fast in the code book
- The commercial and industrial code addresses the residential exam skips, with the sections Oregon amends flagged
- Commercial and industrial math: commercial load calcs, motors, transformers, three-phase
- Worked code math: box fill, voltage drop, conduit fill, ampacity, load calcs, EV charging
- Oregon law and rules, including the J license scope and CE
- A full timed Oregon General Journeyman practice exam
- Lifetime access for this code edition
Look inside
A worked example straight from the “Box Fill” chapter, exactly as it appears in the pack.
Worked example: the one you'll actually see
Here's a box I've wired a thousand times. Kitchen, 14-2 in and 14-2 out, one receptacle, metal device box with internal clamps.
What's in it:
- 14-2 coming in: 1 hot, 1 neutral, 1 ground
- 14-2 going out: 1 hot, 1 neutral, 1 ground
- One duplex receptacle
- Internal cable clamps
- Grounds spliced with a pigtail to the device
Run the five categories:
1. Insulated conductors. Two hots and two neutrals = 4 conductors at #14.
4 × 2.00 = 8.00 cu in
(The grounds are not counted here — they get their own category. And the ground pigtail to the device is free, because it starts and ends in the box.)
2. Internal clamps. One allowance, largest conductor is #14.
1 × 2.00 = 2.00 cu in
3. Support fittings. None.
0.00 cu in
4. Device. One yoke, two allowances, #14 on the yoke.
2 × 2.00 = 4.00 cu in
5. Grounds. Two #14 EGCs — one single allowance.
1 × 2.00 = 2.00 cu in
Total required: 8.00 + 2.00 + 0.00 + 4.00 + 2.00 = 16.00 cu in
Now look at the box table. A 3" × 2" × 3½" device box is 18.0 cu in — that works. A 3" × 2" × 2¾" box is 14.0 cu in — that does not.
And that right there is why the deep boxes are worth carrying on the truck. A standard two-cable, one-device kitchen box needs 16 cubic inches and half the device boxes at the supply house don't have it.
What's inside
- 01Navigating the Code Book
- 02The Oregon General Journeyman Exam
- 03Box FillRead it free
- 04Voltage Drop
- 05Conduit Fill
- 06Ampacity
- 07Residential Load Calculation
- 08EV Charging
- 09Journeyman Calculations: Commercial Loads, Motors, Transformers and Three-Phase
- 10Appendix — Preparing Your Code Book
- 11Oregon Law, Rules & Amendments
- 12Answers — Check Yourself
Read online, or download every chapter as one PDF to print.
- Oregon General Journeyman Practice Exam · 52 questions · 180 minutes · Open book